References
Botswana Power Corporation, Botswana
Simulator training program for operation engineers
STEAG Energy Services India (SESI) was awarded the contract to provide the following services:
- Leasing of the simulator for coal-fired power plant operators training for a period of one year.
- Conducting 13 two-week simulator training programs for operation engineers of Morupule A and B power station.
Project facts
Installed capacity | Morupule A - 4 x 30 MW, Morupule B - 4 x 150 MW |
Technology | Pulverized fuel fired boiler & CFBC Technology |
Customer | Botswana Power Corporation |
Execution of SESI services | 2017 |