• EN
  • References

    Chhabra Power Plant, India

    Prediction and early detection of critical conditions and process behaviors

    At Unit 1 and 3 of Chhabra power plant, STEAG Energy Services (SES) implemented the IT solution SR::SPC to reliably detect changes in the operating behavior. More than 50 key performance indicators (KPIs) were implemented, relieving the operating staff in the continuous assessment of the actual plant condition.

    The SR::SPC system allows cost savings owing to plannable maintenance operations and prevention of unplanned shutdowns.

    Project facts

    Installed capacity3 x 250 MW
    Implemented IT solutionPredictive Analytics (SR::SPC)
    Technologycoal-fired power plant
    CustomerRRVUNL (India)
    Execution of SES services2012 - 2015