• EN
  • References

    Botswana Power Corporation, Botswana

    Simulator training program for operation engineers

    STEAG Energy Services India (SESI) was awarded the contract to provide the following services:

    • Leasing of the simulator for coal-fired power plant operators training for a period of one year.
    • Conducting 13 two-week simulator training programs for operation  engineers of Morupule A and B power station.

    Project facts

    Installed capacityMorupule A - 4 x 30 MW, Morupule B - 4 x 150 MW
    TechnologyPulverized fuel fired boiler & CFBC Technology
    CustomerBotswana Power Corporation
    Execution of SESI services2017