• EN
  • References

    Kashipur CCPP, Uttrakhand, India

    Comprehensive Operation & Maintenance of gas-based combined-cycle power plant

    STEAG Energy Services India (SESI) was awarded the Operation & Maintenance contract by Gama InfrapropPrivate Limited for its 225 MW gas-based combined cycle power plant. The contractual obligations involve the O&M of two gas turbines, related HRSGs and one steam turbine.

    Project facts

    Installed capacity225 MW
    Technology2 GT 75 MW GE (6FAe)
    1 ST 72 MW HTC
    HRSG I & II Thermax
    Fuelnatural gasand R-LNG supplied by GAIL
    CustomerGama Infraprop(P) Limited of RLG Group
    Execution of SESI services11/2015 - 01/2020