References
Power Plants STEAG GmbH, Germany
Realization of 90 MW battery storage system (6 x 15 MW) for primary control reserve
The team of SES engineers was responsible for the technical planning and realization of the large-scale battery systems. The specialists worked closely with the general contractor Nidec, the battery cell supplier LG Chemand the construction company. The SES scope of work included (selection): efficiency & investment planning, procurement planning, construction & commissioning supervision, authority permission engineering and integration into the I&C systems.
Project facts
Total storage capacity | 90 MW (6 x 15 MW) |
Overall project value | ca. 100 million Euro |
Customer | STEAG GmbH |
SES project execution | 11/2015 - ongoing |