References
Thermal Solar Power Plant, Spain
Implementing a live CMMS during operation within a very short period of time
The CMMS SI®/PAM was implemented on the basis of a minimal plant index and without predefined preventive maintenance measures. In addition, there was no ERP system at the site yet. At first, the pre-installation of the solution package “Operation & Maintenance“ of SI®/PAM took place on a platform accessible via the Internet in order to interactively inform about the progress of the project in each phase. In parallel, the data for the migration into the CMMS were prepared. Even before the operation management by SES started, the implementation workshop on SI®/PAM took place where also the organizational structure for operation management and maintenance was set up. In the course of this work, among other things all available plant data were imported into the CMMS. As early as six days after the workshop, the implementation of SI®/PAM as a live CMMS was achieved.
Project facts
Installed capacity | 49.9 MW net |
Installed IT solution | CMMS SI®/PAM |
Technology | Steam turbine: General Electric Mirror field: 156 loops / 510,120 m² Salt storage system: 24,500 t |
Customer | Arenales Solar PS, S.L. |
Execution of SES services | 2013 |