    UTG Gas Treatment Plant in Parnaiba, Brazil

    Owner’s Engineer: UTE Parnaiba – thermal power plant (gas)

    STEAG Energy Services do Brasil was hired by ENEVA to perform the following services:

    • Owner‘s engineering 
    • Preparation and validation: design & technical specification 
    • Support to project management 
    • Support to the management of the EPC contractor 
    • Design review 
    • Quality assurance in the process of construction and assembly 
    • Commissioning support

    Project facts

    Installed capacity1.4 GW Open cycles: 855 MW Combined cycle: 520 MW
    CommissioningOpen cycle – 2014 Combined cycle – 2015
    CustomerENEVA
    Execution of SES services2011 – 2016